Site Profile(as of June 2024)
Address | 1-1 Daikyo-cho, Yokkaichi, Mie |
---|---|
Start-up | July 1943 |
Total area | 1,018,340 m2 |
Employees | 422 (as of March 31, 2024) |
Capacity | 86,000 barrels/day |
ISO 9001 | March 14, 1997 |
ISO 14001 | March 20, 1998 |
Images
Site Area
1,018,340 m² |
Capacity of Major Equipment
No.6 Topping Unit | 86,000 barrels / day |
---|---|
No.3 Vacuum Distillation Unit (for Lubricating Oil) |
14,000 barrels / day |
No.5 Vacuum Flasher Unit | 60,000 barrels / day |
No.2 Mild Hydro Cracking Unit | 24,000 barrels / day |
No.1 Sulfur Recovery Unit | 100 t / day |
No.2 Sulfur Recovery Unit | 100 t / day |
Hydrogen Producing Unit | 320,000 m3N / day |
Hydrogen Recovery Unit | 55,500 m3N / day |
Light Naphtha Hydrodesulfurization Unit | 7,000 barrels / day |
No.3 Kerosene & Gas Oil Hydrodesulfurization Unit | 35,000 barrels / day |
No.4 Kerosene & Gas Oil Hydrodesulfurization Unit | 30,000 barrels / day |
No.2 Catalytic Reformer | 8,000 barrels / day |
No.2 Reformate Splitter | 5,900 barrels / day |
No.3 Catalytic Reformer (Contimuous regeneration units) |
13,500 barrels / day |
No.3 Reformate Splitter | 10,500 barrels / day |
Mixed-xylene Distillation Unit | 16,500 barrels / day |
Fluid Catalytic Cracking Unit | 31,000 barrels / day |
FCC Gasoline Hydrodesulfurization Unit | 18,000 barrels / day |
No.1 Benzol-Ketone Dewaxing Unit | 1,550 barrels / day |
No.2 Benzol-Ketone Dewaxing Unit | 3,000 barrels / day |
No.1 Furfural Extraction Unit | 1,800 barrels / day |
No.2 Furfural Extraction Unit |
4,850 barrels / day |
Filter Press Dewaxing Unit |
2,140 barrels / day |
No.1 Lubricating Oil Hydrofinishing Unit |
4,000 barrels / day |
No.2 Lubricating Oil Hydrofinishing Unit |
2,800 barrels / day |
Asphalt Unit |
1,300 t / day |
Tail Gas Treating Unit |
432,000 m3N / hour |
Power Facilities
Boilers | 2 units | 96 t / hour |
---|---|---|
Power Receiving Equipment | 1 unit | 45,000 kVA |
No.1 Co-generation Unit | 17,500 kW 106 t / hour |
|
No.2 Co-generation Unit | 17,500 kW 59 t / hour |
Oil Storage Facilities
Crude Oil Tanks | 11 units | 874,112 kl |
---|---|---|
Finished Product / Semi-processed Product Tanks |
110 units | 1,012,559kl |
Lubricating Oil Tanks | 145 units | 92,000 kl |
Sulfur Tanks | 2 units | 1,190 kl |
Asphalt Tanks | 15 units | 52,330 kl |
LPG Tanks | 15 units | 30,802 kl |
Port Facilities
Crude Oil Tanker Berth | 1 unit | 314,250 DWT |
---|---|---|
Loading / Unloading Piers | 21 units |
Yokkaichi Kasumi Power Station
Site Area
151,253 m2 |
Kasumi Power Generating Unit
Kasumi Power Generating Unit | 230,000 kW |
---|